How to read a BOQ for a house in Sri Lanka

How to read a BOQ.

A bill of quantities is the most useful document in your build, and the one most owners skim. Here is how to read one, section by section, and what to check before you sign.

Published 12 November 2026

Written by Madusha Hapuarachchi, Quantity Surveyor

The short answer

  • A BOQ (bill of quantities) lists every part of the work, measured from the drawings, with a quantity, a unit and a rate for each line.
  • Read it in four passes: what is included, how much of each thing, what each thing costs, and what is left as an allowance.
  • Two prices for the same house can differ by millions because one leaves things out. A BOQ is how you find out what.
  • Never compare contractors on a rate per square foot alone. Compare BOQs line by line.

A BOQ at a glance

Most house BOQs in Sri Lanka follow the order of the build. The names vary between quantity surveyors, but the sections look like this:

Section (bill)What it coversWhat to check
PreliminariesSite set-up, temporary water and power, insurance, site supervisionIs supervision included, and for how long?
SubstructureExcavation, footings, plinth beam, damp-proofing, fillingExcavation depth and soil assumptions
SuperstructureColumns, beams, slabs, staircase, blockwork or brickworkConcrete grade and steel quantities
RoofRoof slab or timber/steel roof structure, sheets or tiles, guttersWaterproofing on a flat roof
Doors and windowsFrames, shutters, glass, ironmongeryTimber species or aluminium profile named
FinishesPlaster, floor and wall tiles, ceilings, paintTiles priced, or left as an allowance?
ServicesPlumbing, drainage, electrical wiring and pointsNumber of points, fittings included or not
External worksDrains, soakage pit, septic tank, pavingOften missing from cheap quotes
Provisional sums and allowancesAmounts for items not yet chosenAre they realistic for your taste?

How to read one line

Every line has the same five parts. Take a typical concrete item:

  • Description: what the work is and how it must be done, for example "Grade 25 concrete in ground-floor slab, 125 mm thick, including curing".
  • Unit: how it is measured: m³ for concrete, m² for plaster and tiles, m for skirting, kg for steel, "No." for doors and fittings.
  • Quantity: how much, measured from the drawings.
  • Rate: the price for one unit, including materials, labour and the contractor's overheads.
  • Amount: quantity × rate.

The description matters as much as the number. "Plaster to walls" and "15 mm plaster to walls, in two coats, finished smooth" are not the same item, and the first gives a contractor room to do less.

Eight things to check before you sign

  1. It matches your drawings. Room sizes, number of floors, roof type and the number of bathrooms should all agree with the latest drawings.
  2. Nothing big is missing. Look for septic tank and soakage pit, drains, water tank, staircase, parapet walls and waterproofing.
  3. Materials are named. Concrete grade, steel type, block or brick size, timber species, tile size. "Good quality" is not a specification.
  4. Allowances are realistic. If tiles are allowed at a low price per square metre and you like large-format porcelain, the gap becomes an extra.
  5. Electrical and plumbing points are counted. Count the switches, sockets and taps you want, and compare.
  6. Preliminaries are there. Supervision, site security and insurance cost money. A BOQ without them hides the cost elsewhere.
  7. The totals add up. Check a few lines with a calculator. Mistakes happen, in both directions.
  8. It says how changes are priced. Variations should be priced at the BOQ rates where a similar item exists.

Good to know: provisional sums are not savings. They are placeholders. Ask what each one assumes, and raise it if your taste is different.

Comparing two contractors' prices

When one price is much lower, the difference is almost always in one of four places:

  • Scope: items left out, usually external works, waterproofing, the staircase finish or the water tank.
  • Specification: a lower concrete grade, thinner plaster, smaller tiles or lighter aluminium.
  • Allowances: low provisional sums that will be topped up later.
  • Quantities: measured short, so the final account grows as the real quantities appear.

Put the two BOQs side by side, section by section. If a contractor will only give you a rate per square foot, ask what it includes, in writing.

Using the BOQ during the build

A good BOQ keeps working after you sign. Each bill should show what was measured on site against the BOQ lines, at the BOQ rates. That way you pay for work that exists, and you can see at any time how much of the budget is spent and how much work is left.

At GRIT, every BOQ is prepared in-house by our quantity surveyor, line by line, and we guarantee 95% BOQ accuracy on the agreed scope; variations are priced separately.

Key takeaways

  • A BOQ lists every item with a description, unit, quantity, rate and amount.
  • Check it against your latest drawings before anything else.
  • Named materials and counted points protect you more than a low total.
  • Allowances and provisional sums are placeholders, not savings.
  • Compare contractors on BOQs, not on a rate per square foot.
  • Pay against work measured on site at the BOQ rates.

Questions people ask

What is a BOQ in house construction?

A bill of quantities is a document that lists every part of the building work, measured from the drawings, with a rate and an amount for each item. It is the basis for pricing, comparing contractors and paying for work as it is done.

Who prepares a BOQ in Sri Lanka?

A quantity surveyor, working from the architectural and structural drawings. Some contractors prepare their own; an independent or in-house QS should still check it.

Can I get a BOQ without drawings?

Not an accurate one. You can get a rough estimate from room sizes and finishes, but the BOQ needs dimensioned drawings and a finish specification.

Why is my BOQ higher than the rate per square foot I was told?

A rate per square foot usually leaves things out: external works, the septic tank, waterproofing or the finishes you actually want. The BOQ shows the complete picture.

How accurate is a BOQ?

As accurate as the drawings and the specification behind it. Changes to the design after the BOQ is prepared are variations and are priced separately.